Petitioner
National Power Corporation
Respondent
Hon. Court of Appeals
Citation
G.R. No. 107631
Court
Supreme Court
Division
Third Division
Ponente
Francisco, J.
Decided
February 26, 1996

Summary

This case involves a contractual dispute between National Power Corporation and PECORP, Inc. over fee claims under a cost-plus construction contract for Mariveles Dam No. 1. The main issue was whether two specific claims could be arbitrated: fees for drilling and grouting work that NPC contracted separately with another company, and fees for minimum guaranteed equipment rental. NPC argued these claims were not arbitrable, invoking Civil Code Article 1725 and claiming PECORP withdrew one claim. The Supreme Court affirmed lower courts' decisions requiring arbitration of all claims, holding that the contract's arbitration clause covers any disputes arising from the contract without qualification. The Court rejected NPC's Article 1725 defense, finding no actual withdrawal from construction but merely a transfer of work. The case establishes the broad scope of contractual arbitration clauses and limits on unilateral contract modifications.

Statutes applied

Search Philippine case law on Intellegal →

By the Intellegal Editorial Board · February 26, 1996

Search Philippine case law on Intellegal →
AI-assisted case analysis — for research only. Verify against the official decision. A research aid, not legal advice; using this page creates no attorney-client relationship. For legal advice, consult a Philippine lawyer. Verify every holding and citation against the official decision (Supreme Court E-Library / Official Gazette) before relying on it.