Petitioner
Market Developers
Respondent
Hon. Intermediate Appellate Court
Citation
G.R. No. 74978
Court
Supreme Court
Division
First Division
Ponente
Cruz, J.
Decided
September 8, 1989

Summary

MADE and Uy entered a written shipping contract for cargo transport from Iligan City to Kalibo, Aklan with demurrage provisions. They subsequently agreed orally to divert the cargo to Roxas City. After unloading, Uy demanded demurrage charges claiming an 8-day delay. The Supreme Court reversed lower court decisions, ruling that the original written contract was replaced by a valid oral contract when the destination changed substantially. Since port conditions differed between the two locations, demurrage terms could not be automatically carried over. The Court found insufficient evidence of actual delay and noted Uy's suspicious 6-month delay in demanding payment. This case establishes the validity of oral shipping contracts under the Code of Commerce and demonstrates that substantial contract modifications can create new agreements superseding original written terms.

Statutes applied

Related cases

Other Philippine cases on the same provisions and issues.

Search Philippine case law on Intellegal →

By the Intellegal Editorial Board · September 8, 1989

Search Philippine case law on Intellegal →
AI-assisted case analysis — for research only. Verify against the official decision. A research aid, not legal advice; using this page creates no attorney-client relationship. For legal advice, consult a Philippine lawyer. Verify every holding and citation against the official decision (Supreme Court E-Library / Official Gazette) before relying on it.